American Track was contracted to do a design/build project for CIG’s frack sand unloading project. We did the complete design for civil, drainage & track. The client had a rigid deadline for completion. We surpassed expectations and finished the project 71 days ahead of schedule.
- 26,929 Track Feet using steel ties
- 9 No. 9 Turnouts
- 1 No. 10 Turnout
- Installation of catch basins & storm drainage system
- Earthen bumpers
- Road crossings
- Roads between tracks
- Driveways
- Truck staging area