Three-Week Project

Lead by Area Manager, Mike Hansen, and Superintendent, Juan Vigil, our Salt Lake City, Utah crews recently completed this three-week project for a customer in Nampa, Idaho.

This project consisted of:

🛤️ Removal of (2) #9 turnouts and 880 TF of ballasted track

🛤️ Installation of (2) #9 turnouts per Union Pacific Railroad’s standards

🛤️ 250 TF of new construction

🛤️ Installation of 300 FT of relay rail, 300 crossties, and (2) new concrete crossings

Great work, Mike, Juan, and crew! 🥳